Submittals and Architect Responsibility

Submittals are NOT contract documents, but are only to demonstrate the way that the contractor proposes to conform with the design concept in the contract documents.

Pursuant to AIA A201 2007: 3.12.4 Shop Drawings, Product Data, Samples and similar submittals are not Contract Documents. Their purpose is to demonstrate the way by which the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals. Review by the Architect is subject to the limitations of Section 4.2. 7. Informational submittals upon which the Architect is not expected to take responsive action may be so identified in the Contract Documents. Submittals that are not required by the Contract Documents may be returned by the Architect without action.

 

The contractor is required to note any deviations from the contract documents in the submittals, so that the change can be approved by the architect or issued in a change order with approval by the owner. Any deviations from the contractor documents that are included in the submittals are not acceptable and the contractor is responsible for correcting the deviation.

Pursuant to A201 2007: 3.12.8 The Work shall be in accordance with approved submittals except that the Contractor shall not be relieved of responsibility for deviations from requirements of the Contract Documents by the Architect's approval of Shop Drawings, Product Data, Samples or similar submittals unless the Contractor has specifically informed the Architect in writing of such deviation at the time of submittal and (l) the Architect has given written approval to the specific deviation as a minor change in the Work, or (2) a Change Order or Construction Change Directive has been issued authorizing the deviation. The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples or similar submittals by the Architect's approval thereof.

The architect and engineer only reviews the submittals for general conformance with the contract documents, as noted on their stamps. The contractor is responsible for conforming to the contract documents.

Pursuant to A201 2007: 4.2.7 The Architect will review and approve, or take other appropriate action upon, the Contractor's submittals such as Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. The Architect's action will be taken in accordance with the submittal schedule approved by the Architect or, in the absence of an approved submittal schedule, with reasonable promptness while allowing sufficient time in the Architect's professional judgment to permit adequate review. Review of such submittals is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain the responsibility of the Contractor as required by the Contract Documents. The Architect's review of the Contractor's submittals shall not relieve the Contractor of the obligations under Sections 3.3, 3.5 and 3.12. The Architect's review shall not constitute approval of safety precautions or, unless otherwise specifically stated by the Architect, of any construction means, methods, techniques, sequences or procedures. Tue Architect's approval of a specific item shall not indicate approval of an assembly of which the item is a component.

 

DRH Design
http://www.drhdesign.com

Comments

Popular posts from this blog

The Deepest Dive - Summary

It was called the inverted moon landing. The deepest work dives ever. It was the dive that would make Norway unimaginably rich. In retrospect, it was called a success. How was it possible when one died, one was injured and a third party as far as my life is preserved? http://www.nrk.no/dokumentar/xl/det-dypeste-dykket-1.12601303

Prosecutors did not know the truth

The prosecutor who dismissed Skånevik case never got to know that the Labour Inspectorate allowed divers to operate without reserve air. A young American died during a record dive. Now requires more that the case is resumed.